A-5 Tunnel to Open Dec. 23 After 43-Day M-30 Link Closure
Madrid's A-5 tunnel is due to open Dec. 23 after a 43-day closure of the M-30 link. See the dates, the bus and Metro boosts and what comes next.

The Ayuntamiento de Madrid (Madrid City Council) says the new A-5 tunnel will open to traffic on Dec. 23, 2026. Until then, the connections between the A-5 and the M-30 ring road stay closed in both directions, as reported by Madrid media.
The closure began on Nov. 10 and is planned to last 43 days. Drivers can still use the A-5 on the surface, where two lanes per direction remain open around the works, but they cannot use the usual slip roads to and from the M-30.
What the closure is for
Crews are finishing the last 172 meters of the underground route. The job, known as the entronque (the junction between two tunnels), means changing a structure that already carries traffic under the avenida de Portugal, so it has to be done without weakening it.
Workers are removing the old connecting ramp and digging out a large volume of earth. They then place the beams that will cover the new section: 142 precast beams, each about 30 meters long.
Dates to know
- Nov. 10: the A-5 and M-30 connection closed completely.
- Dec. 23: planned opening of the tunnel and return of the link to the M-30.
- Early 2028: planned finish of the Paseo Verde del Suroeste, the surface park project.
Alternatives while the link is shut
The council has set out detours via the M-40 and other access roads. It has also strengthened public transport: EMT buses on lines 31, 36, 39, 138 and 158 run more often, and Metro lines 3 and 10 have extra service. Intercity buses linking Madrid with Alcorcón, Móstoles and Navalcarnero also get reinforcements.
Why it matters
Mayor José Luis Martínez Almeida announced the opening date and said vehicles will be able to use the fully underground route earlier than the original schedule foresaw. According to the council’s estimates, about 90% of the vehicles that use the road each day will be able to drive underground.
Once traffic moves below, work continues on the surface. The Paseo Verde del Suroeste covers roughly 3.2 kilometers and adds new public space. Part of the space now taken by the road is to become gardens, pedestrian routes and bike lanes, reconnecting the neighborhoods of southwest Madrid that the A-5 has split for years.
Source: 20minutos