Spain Approves Data Center Decree Requiring 80% New Renewables
Spain's cabinet approved a data center decree requiring 80% new renewable power matched hourly. The industry calls it unworkable and plans a court challenge.

Spain’s government approved a royal decree on Friday that sets sustainability rules for large data centers, keeping the two requirements the industry calls unworkable. Under the text, adopted at an extraordinary meeting of the Consejo de Ministros (Spain’s cabinet), big facilities must cover 80% of their electricity use with newly built renewable capacity, matched hour by hour. According to El Correo, the approval came nine days before the Nov. 29 general election.
Spain DC, the trade group whose members include Amazon, Microsoft and Google, opposes the decree. It says about €9.000 million in investment has been withdrawn or frozen since the first draft appeared, and warns that projects will move to Portugal or southern France.
What the decree requires
The rules apply to data centers above 10 megawatts. The first draft started at 1 megawatt. The main obligations are:
- 80% of consumption must come from additional renewable capacity, meaning new plants rather than existing ones, and the power must be used in the same hour it is generated.
- Facilities must be able to be disconnected when the grid is under strain.
- Every data center must reach category A of the European water efficiency label, with an energy efficiency threshold that depends on the climate region where the site sits.
20 minutos reports that “new” plants can be at most 36 months old, up from 18 months in an earlier version. Solar farms can be older if they sign long-term power purchase agreements.
The voluntary transition regime
To ease the change, the decree offers a voluntary transition regime. According to 20 minutos, centers that opt in start at 60% hourly renewable consumption, move to 70% in 2029 and must reach 80% on Jan. 1, 2032. In exchange they must join the demand response service and be the first to be switched off when Red Eléctrica, the grid operator, needs to. The sector rejects both routes. Spain DC spokesperson Begoña Villacís has said she sees either option as unacceptable.
Why the government says it acted
Sara Aagesen, the minister for the ecological transition, said data centers already hold 15 gigawatts of grid access permits, 6 for transmission and 9 for distribution. Another 3 gigawatts were added in the last three months, and 20 gigawatts more are waiting. She put the 15 gigawatts at roughly 40% of peak electricity demand on the mainland.
Without the decree, the government calculates, gas use for power generation would rise 165%. That would add €4.000 million a year to wholesale prices and €1.000 million for the capacity mechanism, a total of €5.000 million, and industrial consumers’ bills would go up 25%. Aagesen called the scenario conservative because it leaves out the wars in Ukraine and the Middle East. She said the rules would make Spain a world pioneer. She also acknowledged that the 2024 artificial intelligence strategy estimated needs well below today’s reality. The sector expects to invest more than €60.000 million over five years.
What the industry and the opposition say
Equinix runs on 100% renewable energy in Europe and operates eight data centers in Madrid and Barcelona. Its Spain managing director, Valentín Pinuaga, called hourly matching a demanding requirement and asked that existing investments and contracts be respected.
The decree was not notified to the European Commission under the TRIS procedure, which covers technical rules that can affect the single market and usually delays approval by about three months. The government says it was not necessary and points to France, Germany and the Netherlands, which regulated without it. Spain DC will take the decree to the Tribunal Supremo (Supreme Court). It also hopes for a change of government after the election, with the PP and Vox ahead in polls according to El Correo. Alberto Nadal of the PP said his party would repeal the decree.
The grid plan approved alongside it
The same meeting approved the transmission grid plan to 2030, with €17.146 million in investment and 6.706 kilometers of new lines. According to El Correo, Madrid and Aragón consider it insufficient for their digital hubs. 20 minutos reports that the plan allows 47.700 megawatts of new demand to connect, after the connection capacity offered to regions rose from 27.700, with Aragón, the Comunidad de Madrid and Andalucía receiving the most.
What this means for Madrid
Madrid is one of the regions pressing for more grid capacity for its data center sector. Whether the decree survives will depend on the courts and on the government that takes office after Nov. 29.
Sources: El Correo, 20 minutos